Gravel and Crushed Stone Calculator: Tons, Cubic Yards and Bags
Gravel is sold by the ton and laid by the compacted cubic yard, and the number that joins the two is a density that changes with the material. This gives you both, from published conversion factors, and takes the figure off your delivery ticket when you have one.
When the figures look right, the aggregate material list downloads as a real PDF with your business details on it, built inside your own browser. Nothing you type is uploaded anywhere.
Worked example
These are the figures the calculator opens with and the answer it gives. Change anything above and every number below moves with it.
- ShapeRectangle, or a trench
- Length or diameter40 ft
- Width, ignored on a circle12 ft
- Compacted depth4 in
- MaterialCrushed base, 3/4 in
- Tons a cubic yard from your ticket, 0 to use the published figure0
Order this much10.84 tons
The factor for dense graded base, 3/4 inch is published as a range, 1.80 to 1.86 tons a cubic yard, not as one figure. This uses the midpoint 1.83, so the tonnage above can be out by about 1.6 percent either way, which is 0.18 tons on this job. Your delivery ticket has the real figure for that quarry.
| Area | 480 sq ft40 by 12 ft |
|---|---|
| Volume in place, compacted | 5.93 cu yd4 in deep |
| Tons a cubic yard used | 1.83midpoint of the published 1.80 to 1.86 |
| Order by the ton | 10.84 tons |
| Order by the loose cubic yard | 8.39 cu ydcompacted to loose is 36 to 47 percent for this material |
| One ton covers | 44 sq ftat 4 in compacted |
| A cubic yard weighs | 3,660 lb |
| Total weight | 21,689 lb |
| Half cu ft bags, if bagging it | 453figured on the loose volume |
The material list this produces
| dense graded base, 3/4 inch, tons | 11 |
|---|---|
| dense graded base, 3/4 inch, loose cu yd | 8 |
| Geotextile fabric under the base, sq ft | 480 |
| Compactor, days | 1 |
| Truck loads at 20 tons, each | 1 |
What this calculator assumes
- Aggregate is bought by the ton and placed by the compacted cubic yard, and the number that joins the two is a density that varies by quarry. This page computes the compacted volume in place and multiplies it by a conversion factor in tons per compacted cubic yard.
- The conversion factors and the compacted to loose expansion percentages come from Wisconsin DOT and Wisconsin Highway Research Program report 0092-22-05, which measured them for nine named materials and published each one as a range rather than as a single figure. The page uses the midpoint and prints the range beside it.
- If you buy by the ton, compaction does not change your order: the tonnage is the compacted volume times the factor either way. If you buy by the loose cubic yard it does, because a loose yard on the truck becomes less than a yard in the ground, and the expansion percentage is what tells you how much less.
- Depth is the compacted depth of the finished layer, not the depth of the loose material before it is rolled.
- Bag counts are for the half cubic foot bags sold at the box stores, and they are figured on the loose volume, because a bag holds loose material.
- The figures were measured in Wisconsin. The report itself notes that only about 23 percent of the DOTs it surveyed use conversion factors for aggregates at all, and that some materials needed region specific factors. Put the figure from your own delivery ticket in the last field and the page uses that instead.
Tons or yards, and why you need both
The quarry weighs the truck, so the ticket says tons. The plan says depth, so the job is measured in compacted cubic yards. Everything that goes wrong with a gravel order happens in the gap between those two units, and the number that closes it is a conversion factor in tons per compacted cubic yard.
That factor is not a constant. Wisconsin DOT and the Wisconsin Highway Research Program measured it for nine named aggregates in report 0092-22-05 and found the whole set ran from 1.50 to 1.98 tons per compacted cubic yard. At one end, structure backfill of sand and gravel. At the other, dense graded crushed base in the 1 1/4 inch size. Use one figure for both and a 20 ton order is out by 6 tons.
So this page asks which material, prints the published range beside whichever figure it used, and leaves a field for the number on your own delivery ticket. Put that in and the answer stops being an estimate.
The same pile has three different volumes
Aggregate passes through three states on the way to the job, and the report names all three: bank, which is the material still in the ground or in the face; loose, which is stockpile and hauling; and compacted, which is what you are paid for. A cubic yard in one state is not a cubic yard in another.
Compacted to loose runs from 27 to 60 percent depending on the material, which is the number almost nobody publishes. Breaker run swells 27 to 30 percent. Recycled concrete base swells 37 to 60. That is the difference between a full load and two trips.
Which one matters to you depends entirely on how you buy. If you buy by the ton, compaction does not change your order at all: compacted volume times the compacted conversion factor is the tonnage either way, and the scale does not care how fluffy the pile was. If you buy by the loose cubic yard it changes everything, because the yard you pay for on the truck is not the yard that ends up in the ground.
Why a range and not one clean number
A single figure would be easier to read and it would be worse. The report published each factor as a range because that is what the testing produced, and the spread is real: a quarry in one region and a quarry in another are not selling the same rock, and the report found that some of these materials needed region specific factors.
It also found that only about 23 percent of the state DOTs it surveyed use conversion factors for aggregates at all. Most of the industry is working off whatever number the yard says. Getting a measured range and knowing how wide it is beats getting a confident figure from nowhere.
These are Wisconsin numbers and this page says so on the page rather than in the small print. They are the best free published figures available, and they are not the figure for your quarry. The ticket is.
What the depth is actually measuring
Depth here is the finished compacted depth of the layer, not the height of the loose pile before it is rolled. Enter the layer you want to end up with and the page works backwards to the truck.
A driveway base is usually 4 to 8 inches of crushed material over fabric, a patio or paver base 4 to 6, and a french drain or a trench backfill is whatever the detail says. Under 2 inches compacted, no aggregate holds together under a wheel load, and the page says so.
Anything over about 4 inches goes down in lifts, because a plate compactor cannot reach the bottom of a deeper layer. Two four inch lifts compact properly. One eight inch lift settles later, usually in a wheel track, usually after you have been paid and gone.
Questions people ask
How many tons of gravel are in a cubic yard?
It depends on the material, and the measured spread is wide: WisDOT report 0092-22-05 puts nine named aggregates between 1.50 and 1.98 tons per compacted cubic yard. Dense graded crushed base in the 3/4 inch size is 1.80 to 1.86, breaker run 1.82 to 1.87, structure backfill of sand and gravel 1.50 to 1.72. Pick the material above and the page prints the range it used.
Does compaction change how much gravel I should order?
Only if you buy by the loose cubic yard. Buying by the ton, it makes no difference: the compacted volume times the compacted conversion factor is the tonnage whatever state the pile was in when it was loaded. Buying by the loose yard it matters a lot, because the same material swells 27 to 60 percent from compacted to loose depending on which one it is, and that is the volume that has to fit on the truck.
How much gravel do I need for a driveway?
Length times width times depth in feet, divided by 27, gives the compacted cubic yards, then multiply by the conversion factor for tons. A 40 by 12 foot driveway at 4 inches of 3/4 inch crushed base is 5.93 compacted cubic yards, which is about 10.8 tons at the published midpoint of 1.83, or 8.4 loose cubic yards on the truck.
How much does a cubic yard of gravel weigh?
Between about 3,000 and 3,960 pounds compacted, which is the 1.50 to 1.98 tons per cubic yard range doubled. Crushed base in the 3/4 inch size works out around 3,660 pounds a yard. A half ton pickup should not be asked to carry one.
How many bags of gravel in a cubic yard?
Fifty four of the half cubic foot bags, since a cubic yard is 27 cubic feet. Bags hold loose material, so the count on this page is figured on the loose volume rather than the compacted one. Below about one loose yard, bags usually beat the minimum delivery charge.
Free Contractor Estimate Template, free, no signup, PDF Word and Excel.