Retainage Calculator for Progress Payments

Retainage is money you have already earned that somebody else is holding. This works out how much is being held right now, what is payable on this application, and what will be sitting there at closeout.

Contractwork completedstill to doThis drawalready paidretainage heldearned to date, less retainage, less what has already been paid
Retainage is money you have earned and cannot invoice yet, and it stacks up quietly across a job. The page works out what is payable on this application and what is still sitting behind the retainage line at completion.

Worked example

These are the figures the calculator opens with and the answer it gives. Change anything above and every number below moves with it.

  • Contract amount120000 $
  • Retainage10 %
  • Work completed to date60 %
  • Already paid to you54000 $

Payable on this application$10,800.00

Contract amount$120,000.00
Work completed60%
Earned to date$72,000.00
Retainage held at 10%$7,200.00
Less already paid$54,000.00
Due on this application$10,800.00
Retainage held at completion$12,000.00chase this at closeout

What this calculator assumes

  • Retainage is money you have earned that is held back until the job closes out. It is not a discount and it is not a deposit.
  • Most states cap retainage on public work, commonly at 5 or 10 percent, and several require it to be released or reduced at substantial completion. Private contracts are freer and often worse.
  • Retainage is usually the last money a contractor sees and the first thing forgotten at closeout. Track it separately from the invoice balance.

What it is and what it is not

Retainage is a percentage withheld from every progress payment until the job is complete, typically 5 or 10 percent. It is not a deposit, not a discount, and not a contingency. It is your money, earned, held as security for completion.

Track it separately from the invoice balance. It is the last money on the job and the first thing forgotten at closeout, and a contractor who does not track it will eventually write some of it off out of sheer exhaustion.

The squeeze at the bottom of the chain

A 10 percent retainage on a job with a 10 percent margin holds back your entire profit until the day the last punch item is signed off. That is the structural problem with retainage and it is why it hurts subcontractors more than anyone.

Most states cap retainage on public projects, commonly at 5 percent, and many require release or a step down at substantial completion. Private contracts are far freer and often far worse. Read the clause before you sign, because that is the only moment you can change it.

Questions people ask

What is retainage in construction?

A percentage of each progress payment, usually 5 or 10 percent, withheld until the work is complete. It is money you have earned but cannot collect until closeout.

Is retainage legal?

Yes, and it is standard. Most states cap it on public work and many require release at substantial completion. Private contracts are governed mainly by what you signed.

How do I get retainage released?

Complete the punch list, deliver the closeout documents, warranties, as builts, lien waivers from your own subs, and invoice it specifically as retainage release. Vague final invoices sit in a pile.

Need the paperwork too?

Free Contractor Invoice Template, free, no signup, PDF Word and Excel.

Common sizes, worked out

The same calculator with the numbers already filled in, one page per size, each ending in its own material list.

Put this calculator on your own site

Free to embed. The only condition is the one line of credit already in the snippet, and there is no tracking of your visitors beyond a page view. Paste this where you want it to appear. It resizes itself.

It comes light, because most of the pages it goes on are light. If your site is dark, put ?theme=dark on the end of the iframe address, or ?theme=auto to follow whatever each reader has set on their own device.