How Much Concrete for a 40x60 Slab?

Concrete needed

48.89 cubic yards

A 40 by 60 foot slab at six inches, with ten percent on top for waste.

It does not stop at a number.

When the figures look right, the concrete material list downloads as a real PDF with your business details on it, built inside your own browser. Nothing you type is uploaded anywhere.

length, ftthickness, inwidth, ftlength x width x (inches / 12) / 27 = cubic yards
Concrete is priced by the cubic yard and poured by the inch. The calculator turns the thickness into feet, multiplies out the volume, divides by 27, then rounds up to the quarter yard the truck actually sells.

How that number is worked out

These are the figures this page was built with and every line the calculator produces from them. Change anything above and all of it moves.

  • Length40 ft
  • Width60 ft
  • Thickness6 in
  • Waste allowance10 %

Concrete needed48.89 cubic yards

Volume1,200 cu ft
Cubic yards before waste44.44
Cubic yards with 10% waste48.89order to this number
Order in quarter yards49 cu yd
60 lb bags, if bagging it2,934
80 lb bags, if bagging it2,200

The material list this produces

Ready mix concrete, cubic yards49
Rebar or mesh, sq ft of slab2,400
Form lumber, linear ft200

Thickness compared

Thickness is the one number on this page worth arguing about, so here is the same slab at each of the usual four.

ThicknessConcrete needed
4 in32.59 cubic yards
5 in40.74 cubic yards
6 in48.89 cubic yards
8 in65.19 cubic yards

What else matters here

Twenty four hundred square feet is the common pole barn and small commercial shop footprint. At six inches it is nearly fifty yards, five or six trucks, and it is the point at which a slab stops being a homeowner project and becomes a concrete job with a crew, a pump or a laser screed, and a finishing plan written down.

Nobody pours fifty yards in one monolithic piece by hand. It goes in strips, usually the width of the screed setup, with construction joints between them and dowels across those joints so the strips deflect together under load. Getting that layout right before the first truck is most of the work.

Joint spacing on a six inch slab is twelve to fifteen feet, so a 40 by 60 wants roughly a 12 by 15 grid, sixteen panels. Cut them early with a soft cut saw, within hours rather than days, because a slab this large generates enough shrinkage stress to find its own cracks overnight.

What this calculator assumes

  • One cubic yard is 27 cubic feet. A 4 inch slab is one third of a foot thick, not 4.
  • A 60 lb bag yields about 0.45 cubic feet and an 80 lb bag about 0.60. Bags are for small pours only; past about one cubic yard, ready mix is cheaper and far less work.
  • Ready mix is usually sold in quarter yard steps with a short load fee below one yard.

Questions people ask

How many yards of concrete is a 40x60 slab?

44.44 cubic yards at six inches, 48.89 once a ten percent waste allowance is added. At four inches it is 32.6 with waste.

How many trucks for a 40x60 slab?

Five to six at nine or ten yards each. At that volume most suppliers will want the order placed days ahead and will ask about your pump, pour sequence and finishing crew.

Can a 40x60 slab be poured in sections?

Yes, and it normally is. Pour in strips with proper construction joints and dowel bars across them. What you must not do is let a pour that was meant to be continuous accidentally become two, which leaves a cold joint with nothing across it.

Different numbers?

The concrete calculator takes any dimensions you like and hands back the same list.

Other common sizes